Pan Am soccer stadium lawsuit claims defective steel, mismanagement - Action News
Home WebMail Sunday, November 24, 2024, 06:00 AM | Calgary | -12.5°C | Regions Advertise Login | Our platform is in maintenance mode. Some URLs may not be available. |
Hamilton

Pan Am soccer stadium lawsuit claims defective steel, mismanagement

A subcontractor who worked on Hamilton's CIBC Pan Am Soccer Stadium claims in a construction lien the project was mismanaged and that major defects to the structural steel of the stadium drove up costs and delayed the stadium's competition.

Subcontractor claims defective steel caused delays, and that project was 'mismanaged from the outset'

Lancaster Group said in a construction lien lawsuit that there were problems with the structural steel and claims that the project was 'mismanaged' from the outset. (Samantha Craggs/ CBC)

A subcontractor who worked on Hamilton's CIBC Pan Am Soccer Stadium claimsin a lawsuittheproject was mismanaged from the outsetand that major defects to the structural steel of the stadium drove up costs and delayed the stadium's completion.

The Lancaster Group,in aconstruction lien, is suing for $1.84 million, naming Infrastructure Ontario (IO), the City of Hamilton, Ontario Sport Solutions (ONSS) and the three companies that made up the ONSSconstruction consortium:Kenaidan Construction Ltd, BouyguesBuildingCanada and Fengate Capital Management Ltd., as defendants.

The Lancaster group, which says ithad a contract for sheet metal/duct work, claimsit is owed for work done at the site,damages caused by delays and premium wages paid for weekend and night work required in therush to complete the stadium, also known as Tim Hortons Field.

Company claimssteel defects

In itsstatement of claim, filed in March 2015, Lancaster writes that "the Defendant's delayed the Project from the very beginning by mismanaging the labour and materials involved. As a result the project quickly fell behind schedule."

The lawsuit allegesthat there were "major defects" to the structural steel installed at the stadium.

The statement of claim contains allegations that have not been proven in court. No statementsof defense havebeen filed with Hamilton courts.

IO, ONSS and the city havepreviously acknowledgedthat there were some structural changes required to the design while the stadium was under construction, but indicated that the scale of those modifications were normal for a "design-build process." The delays to the stadium's completion have been blamed on a cold winter and a bankruptsubcontractor.

Gregory Stack, Kenaidan's vice-president of business development & design build declined to comment on the lawsuit or its claimswhen contacted by CBC.

IO told CBC News that it istaking steps to remove itself from the claim. Spokesperson Lee Greenberg said the lawsuit "is the result of a lien claim placed against the contractor... As part of our contract with ONSS, the contractor is responsible for vacating liens, not Infrastructure Ontario."

Samuel Gandossi, the projects director atBouygues Building Canada and spokesperson for ONSS, did not return calls or emails.

CourtneyIhnat,Marketing Manager forFengate Capital Management, said the company "was not involved in the design-build or project coordination on this project," and directed questions to IO.

Ducting replaced

Lancaster claims that defects in the steel, as well as issues withconcretepoured out of order, led to itsworkers being forced to rip out ducting it had already installed, valued at nearly $2 million. It says it had to later go back and replace the ducting.

Even access to stadium was rife with problems, Lancaster claims.

"Remarkably, it was often the case that Kenaidan and Bouygues (Building Canada Inc.) failed to even coordinate access to the material elevator among the many sub-trades that required its use," reads the lawsuit. "In or about July of 2014 the Project was dangerously behind schedule and at risk of not being complete in time for the Games."

'Scrambling' to get project on schedule

Lancaster was originally scheduled to complete its work a week before the June 30, 2014 deadline for the stadium's completion, but said because of mismanagement of its work"along with other sub-trades," the defendants were "scrambling to get the project back on schedule."

"In the process, Kenaidan and Bouygues created further delays and costs for Lancaster by causing the sub-trades to work out of sequence, stacking other sub-tradesin areas of the Project where Lancaster was performing the Subcontracting Work, and failing to have required equipment and materials ready when they are needed," reads Lancaster's statement of claim.

A partially complete, and still under-construction, stadium opened on Sept. 1, 2014, just in time for the Canadian Football League's Labour Day Classic. The stadium officially opened on May 22, 2015, more than 10 months overdue. On it's road to completion, there were at least seven targeted completiondates, all of which were missed.

Still unresolved issues

As of the start of the Pan Am Games, the grouphas yet to complete all aspects of the stadium, and there is an ongoingobstructed view seat controversyfor the long-overdue stadium.

Previously, Ontario Sports Solutions, blamed a cold winter for construction delays.

Lancasterclaims in the lawsuit that they are still owed $1.17-million, plus HST,in payments from Kenaidan and Bouygues, and an additional $667,737.84 in costs "due to the delay by Defendants."