Airport Trail's next expansion could start in September - Action News
Home WebMail Friday, November 22, 2024, 11:45 AM | Calgary | -10.8°C | Regions Advertise Login | Our platform is in maintenance mode. Some URLs may not be available. |
Calgary

Airport Trail's next expansion could start in September

Construction on Calgary's Airport Trail could start as early as September of this year, after council approved $38.15 million in funds Thursday for the $153.35-million project.

$153.35-million project set to be completed by 2022

More construction on Calgary's Airport Trail could start as early as September. The tunnel at 96th Avenue, which turns into Airport Trail, opened in 2014. (Scott Dippel/CBC)

Construction on Calgary's Airport Trail could start as early as September of this year, after council approved $38.15 million in funds Thursday for the $153.35-million project.

Prime Minister Justin Trudeau announced $50 million in federal funding for the major roadwaywith the goal ofcreatinga new east-west transportation link for Calgary earlier this month.

Alberta is contributing $27.7 millionand another $20 million is coming from the Calgary Airport Authority.

The remainder of the project's budget will depend on the cost to the city ofpurchasingland needed for two new interchanges at Barlow Trail and 19thStreet N.E. That amount also includes some room for overages built into the project's total estimated cost.

"As it stands now, there is a portion that is unfunded," saidCoun. Shane Keating.

The Calgary Airport Authority said it was committed to splitting the cost of the land acquisition with the city in addition to the$20 million.

Keating said the decision of the federal and provincial governments to fund the project helped convince the city itwas time to move ahead.

Prime Minister Justin Trudeau made an Airport Trail funding announcement, alongside Calgary Mayor Naheed Nenshi, earlier this month. (Julie Debeljak/CBC)

"When the opportunity knocks and you see that there's the future potential savings and future potential growth, which ends up giving you more revenue, then you should shuffle the deck and reorganize things and Ithink that's what we did," he said.

The project will see a new segment of roadbuilt between 36thStreet and 60th Street N.E., with an intersection at Mtis Trail. It will also include the first stage of an interchange at 19thStreet and Airport Trail, along with a new, southbound-to-westbound ramp atStoney Trailand Airport Trail.

Second-phase of project

It's the second phase of the Airport Trail expansion project, following the opening of the620-metre, six-lane Airport Trail tunnelin 2014.

Keating said the city may have jumped the queue a bit by building the tunnel before the rest of the trail, but he said it paid off in future savings.

"What we've got now is a true connection, open on Stoney Trail straight through the airport all the way toDeerfoot. And the land in between can be open for greater potential which gives the city more revenue,"Keatingsaid.

There is an allocation for public art in the project's budgetbut, as the city's public art project is on hold, no plan has yet to be developed for what that art might be.

An estimated 406 construction jobs will be created to get the expansion built. All work on the project is set to be completed by the end of 2022.

With files from Scott Dippel, Dave Dormer