Southeast ring road opening delayed - Action News
Home WebMail Sunday, November 24, 2024, 06:03 AM | Calgary | -12.4°C | Regions Advertise Login | Our platform is in maintenance mode. Some URLs may not be available. |
Calgary

Southeast ring road opening delayed

The southeast portion of Calgarys ring road will not be ready to open on Tuesday as planned, but the contractor is facing a $70,000 daily fine until it is completed.

Contractor in charge of project to be fined $70,000 per day for missing Oct. 1 deadline

Southeast ring road delays

11 years ago
Duration 3:22
The southeast portion of Calgarys ring road will not be ready to open on Tuesday as planned.
The planned Oct. 1 opening of the southeast leg of the ring road has been delayed. (CBC)

The southeast portion of Calgarys ring road will not be ready to open on Tuesday as planned.

The $769-million project extending Stoney Trail past Peigan Trail to Highway 22x has taken three years to build.

Transportation Minister Ric McIver said he's still waiting for a final safety audit report.

Chinook Roads Partnership, the contractor groupwho partnered with the Alberta government on theproject, will be slapped with a $70,000 fine each day the road remains closed beyond Oct 1.

When its finished the 25-kilometre route will run from 17th Avenue southeast to new interchanges at Highway 22x, bringing the ring road to 70 per cent of completion.