Rogers Place to undergo repairs 6 months after opening

Nine exhaust fans on the buildings roof have to be replaced after a piece of one unit broke off and landed in a nearby construction site.

'It pointed out in spades that we had a real major concern and not just a minor concern'

Nine exhaust fans on the roof of Rogers Place have to be replaced after a piece of one of the units broke off and landed in a nearby construction site. (Richard Marion/CBC)

Six months since Rogers Place opened in downtown Edmonton, the city's new arena is in need of repairs.

Nine exhaust fans on the building's roof have to be replaced after a piece of one of the units broke off and landed in a nearby construction site.

"When a fan cracks a fan blade cracks you can hear it, and there was a noise that we heard," Rick Daviss, executive director of the downtown arena project for the City of Edmonton, said at a news conference at city hall Thursday.

"Certainly when one fell off the roof, it pointed out in spades that we had a real major concern and not just a minor concern."

No one was harmed and there was no risk to public safety, Daviss said.

Three of the existing fans will remain in place while the nine faulty units are removed."We feel that three of them will be fine," Daviss said.

"There's been breakages, fan blades have cracked, we've had housings damaged they're just not working the way we thought they would."

A large crane will be required to remove the fan unitsfrom the roof andlift their replacements into place.

That will mean ongoing lane closures on the streets aroundthe arena, beginning the week of March 20 and lastingthree to four days.