Tailings pond plans not part of public hearings

Plans to construct a northern Alberta tailings pond without a berm on its western edge were not required to be ready when public hearings were held into the Horizon oilsands project in fall 2003.
The tailings pond operated by CNRL is located near the Fort McKay First Nation in northern Alberta. ((CBC))
Plans to construct a northern Alberta tailings pond without a berm on its western edge were notrequiredto be ready when public hearings were held into the Horizon oilsands project in fall 2003.

Alberta Environment Minister Rob Renner was asked Tuesday if he was concernedthat the plan to build the pond, operated byCanadian Natural Resources Ltd. (CNRL), with only three berms instead of four wasn'traised at the 2003 hearings.

"The engineering of these tailings ponds are detailed as the project progresses and so the geotechnical work and that wouldn't be available at the conceptual stage," Renner said.

The lack of a fourth berm was raised thisweek by a CBC News investigation thatfound animal tracks heading toward the edge of the pond.

People from the Fort McKay First Nation are concerned that there are no barriers preventing the animals they traditionally hunt and trap from accessing water on the unbermed western side.

A joint federal and provincial panel approvedCNRL's overallHorizon project with 17 conditions on Jan. 27, 2004.

Natural embankment found 'suitable'

Plans to construct the pond with berms on three sides were approved later by Alberta Environment in April 2004. According to the plan, tailings were to be contained on the unbermed western side by a clay base and a slope in the terrain.

Environment Minister Rob Renner speaks to reporters at the Alberta legislature Tuesday. (CBC)
Renner said that after the initial conceptual phase of project approval, "there is then a requirement for the detailed plans to be approved actually by my department through a dam assessment."

"In this particular case, they satisfied our officials that the natural embankment, with the geotechnical information intact, would provide a suitable barrier to tailings," Renner said.

"There have been others that have been approved in a similar fashion, so this isn't a one-off."

An official with Alberta Environment said CNRL was required to advertisethe construction plans for the tailings pond prior to approval in order to give the public a chance to raise any concerns.

Environment Canadaexamining the pond

Environment Canada enforcement officers weresent to inspectthe tailings pond Tuesday byfederal Environment Minister John Baird.

They were expected to fly over the site in a helicopter, but no other details of how they will be conducting their evaluation were released. They were accompanied by a number of enforcement officers from the Alberta government.

Officials with Alberta's Energy Resource Conservation Board did a routine inspection ofthe site two weeks ago, and again on Monday, and found the pond was operating within regulations.

CNRL said its tests show no signs of toxins getting into the groundwater but admitted beavers have been getting into the area.

With files from the CBC's James Hees and Michael Dick