Stadium being ready for Labour Day will be 'a stretch': Ferguson - Action News
Home WebMail Sunday, November 24, 2024, 10:36 AM | Calgary | -15.0°C | Regions Advertise Login | Our platform is in maintenance mode. Some URLs may not be available. |
Hamilton

Stadium being ready for Labour Day will be 'a stretch': Ferguson

Builders have promised that the new Tim Hortons Field stadium will be finished by Labour Day, but a city councillor and veteran of the construction industry says he has his doubts.
Sections of the new Tim Hortons field still won't be finished even if crews do make the labour day game, Coun. Lloyd Ferguson says. (Adam Carter/CBC)

Builders have promised that the new Tim Hortons Field stadium will be finished by Labour Day, but a city councillor and veteran of the construction industry says he has his doubts.

Coun. Lloyd Ferguson of Ancaster heads the citys Pan Am subcommittee. He took a tour of the stadium last week after the opening date was delayed until early December the latest delay in a $145-million project.

Based on what he saw, Ferguson estimates theres only a 75-per cent chance the stadium will be done for the Labour Day Classic, when the Hamilton Tiger-Cats play the Toronto Argonauts.

Theres so much work there, said Ferguson, who spent more than 30 years in the construction industry. There may be less than a 75-per cent chance.

I was surprised by how much work there is left to be done.

The consortium Ontario Sports Solutions (OSS)is building the 22,500-seat stadium, which falls under Infrastructure Ontario (IO). The stadium replaces the former Ivor Wynne stadium. In addition to being the home base for the Tiger-Cats, it will host the soccer games for the 2015 Pan Am Games.

Organizers first reported a two-week delay in January, citing issues with subcontractors and a late December ice storm. That estimate lengthened to six weeks over the spring. By the June 30 deadline, OSS hoped the stadium would be finished by the first Tiger-Cats home game on July 26. OSS now estimates it will be open by Labour Day.

In the meantime, the Tiger-Cats are playing at McMaster University, which caused the team to miss out on a major ESPN broadcast. An agreement dictates that IO pays the Tiger-Cats $1 million per missed home game. As of Aug. 16, they will miss three.

If the stadium opens by Labour Day, Ferguson said, theres lots that wont be done. For example, he said, there wont be concession stands. The priority now is health, fire and safety.

Its going to be a real stretch to be ready, he said. Im not saying it wont. Im saying itll be a stretch.

Maintenance and electrical workers are doing double shifts to ready the stadium, said Terence Foran, IO spokesperson.

IO is withholding $89 million of the project until OSS completes it, he said. Thats the only penalty currently in place for the late finish.

Based on conversations with OSS, theyve assured us theyll meet the Labour Day Classic game, he said.

Outstanding work includes:

  • Guard rails and hand railings.
  • Electrical systems such as broadcast cabling and mechanical systems such as bathroom fixtures.
  • Elevatorinstallation.
  • Concessions (food services) equipment installation.

If the stadium isnt ready for by Labour Day, Ferguson said, hell be upset.

Thats putting it mildly, he said. Im upset anyway. They made it clear in their contract that it would be ready by June 30, and theyre not.