Next phase of pumping station project placed on hold for 3 weeks - Action News
Home WebMail Saturday, November 23, 2024, 06:47 AM | Calgary | -12.2°C | Regions Advertise Login | Our platform is in maintenance mode. Some URLs may not be available. |
Manitoba

Next phase of pumping station project placed on hold for 3 weeks

The next phase of the James Avenue Pumping Station project is on hold for three weeks to allow the city and the developers to hash out their differences over the design.

2 new buildings to rise alongside 106-year-old station as part of $20M redevelopment

Architect Sasa Radulovic addresses Winnipeg city council's property committee, which ultimately held off on making a decision about the second phase of a heritage pumping station redevelopment. (Jeff Stapleton/CBC)

The next phase of the James Avenue Pumping Station project is on hold for three weeksto allow the city and the developers to hash out their differences over the design.

In 2016, heritage restoration specialists BryceAlston and Rick Hofer purchased the 106-year-old pumping station from downtown development agency CentreVenture, which had spent 15 years trying to find a buyer for the heritage building.

The developers are spending $20-million on an adaptive reuse of the structure that's taking place in two phases. As part of the first phase, offices have been installed in the pumping station's rafters, preserving heavymachinery below and allowing views of the enormous steam-era equipment.

The second phase calls for the construction of a new 28-unit residential building proposed for the east side of the building, along Waterfront Drive, and a 63-unit mixed-use building proposed for the west side.

Planners rejected a request for a zoning variance for this phase on the basis the parking is inadequate and an elevator shaft is too close to a neighbouring condominium building.

The developers appealed, leading to a hearing before council's property and development committee on Monday, where planners further told the developers they saw no value in allowing views of the pumping station from Waterfront Drive by raising the 28-unit structure on stilts.

The second phase of the James Avenue Pumping Station redevelopment calls for the construction of two new buildings on either side of the heritage structure. The proposed structures are painted black in this model. (Jeff Stapleton/CBC)

Architect SasaRadulovic of 5468796 Architecture also said he was surprised to learn the city would allow access to the building's main level.

Based on the confusion, the committee voted to hold off on a decision until a special meeting takes place on Dec. 15. Committee chair John Orlikow (River Heights-Fort Garry) said he did not have enough information to make an informed decision.

Radulovic said he plans to meet intensively with city planners over the next three weeks to end an impasse over the project. He said the developers have already made eight concessions.

"I think we're creating a great thing for the city," he said, referring to a project that will preserve an old building and create more housing just north of the Exchange District.