2 South Shore mayors defended Northvolt without knowing environmental impact, letter shows - Action News
Home WebMail Friday, November 22, 2024, 12:15 PM | Calgary | -10.5°C | Regions Advertise Login | Our platform is in maintenance mode. Some URLs may not be available. |
Montreal

2 South Shore mayors defended Northvolt without knowing environmental impact, letter shows

The mayors say they've shown "considerable political courage" in trying toreassure residents and gain social acceptability of the project, all while having no answers to their own questions from the government about the environmental impact of the project.

Mayors had many unanswered questions about impact of EV battery plant

A group of people posing with a Northvolt battery on a stage.
Saint-Basile-le-Grand Mayor Yves Lessard, with a white beard and wearing a grey suit, stands directly in front of McMasterville Mayor Martin Dulac at the announcement of Northvolt's mega-factory slated for their municipalities. (Radio-Canada)

Despite their public endorsement of the Northvolt electric vehicle battery plant, the mayors of two communities on Montreal's South Shore were privately far from certain about their support of the project.

Yves Lessard and Martin Dulac, the mayors ofSaint-Basile-le-Grand andMcMasterville in the Montrgie region, have both expressed their supportfor the controversial $7-billion project, which straddles both municipalities.

"We welcome this arrival on our territory and we are confident that it will be an exemplary project in every respect," said Dulaclast September at the announcement, posing alongsidePrime Minister Justin Trudeau andQuebec Premier Franois Legault with a Northvolt battery in their hands.

In an interview with Radio-Canada, Dulac said he was "reassured" by Northvolt's"very clear" answers on the project's potential environmental impacts.

But in a letter sent to Quebec Environment Minister Benoit Charettein January, obtainedby Radio-Canada through an access to information request, the mayors revealed they knew virtually nothing about the environmental impacts of the proposed mega-factory.

A letter showing the introduction to a letter to Quebec's Environment Ministry from the mayors of Saint-Basile-le-Grand and McMasterville.
The beginning of the letter written by Yves Lessard and Martin Dulac, the respective mayors of Saint-Basile-le-Grand and McMasterville in the Montrgie region, to Environment Minister Benoit Charette. (Radio-Canada)

The mayors voiced their dissatisfaction with the lack of communication from Charette's ministry regarding the construction of Northvolt's plant.

"We are dismayed by your absence and silence, both in discussions with the authorities in our towns and in the public and media sphere," the letter reads.

The mayors say they've shown"considerable political courage" in trying toreassure residents and gain social acceptability for the project, all while having no answers to their own questions about its environmental impact ones they say they've repeatedly asked from the ministry for months.

Although he defended Northvolt to his residents before penning the letter, Lessard had publicly questioned the absence ofan environmentalreviewby the Bureau d'audiences publiques sur l'environnement (BAPE) for a project of this magnitude.

Still, his municipality went ahead withinitiating the process to grant a permit to the company in January.

Mayors defend their positions

Asked to clarify the differences between his public and private statements, the mayor of McMasterville said it was important that the ministry directly meet with residents to address their concerns about the environment impact of the project.

"We were satisfied with the answers we received, but it was not up to the city to take the place of the ministry in responding to environmental issues," Dulac said.

For his part, the mayor ofSaint-Basile-le-Grand saidthe purpose of the letter was to put pressure on the ministry to hold informationsessions for residents of both municipalities something the ministry had initially said would take place in November 2023, but ultimately happened at the end of February,a month after the letter was sent.

During these sessions, officials with the Environment Ministrywere unable to identify the potential pollutants Northvoltmight release into the atmosphere or the river.

Environment Ministry responds

In an email to Radio-Canada, the Environment Ministry saidthe judicialization of the project is what forced officialsto postpone the information sessions, but it had set up a website in the meantime to address citizens' concerns.

"The government ensures it supports and assists municipalities so they have all the necessary information to respond to their citizens' inquiries," the office said.

Meanwhile, the mayors say the unansweredconcerns raised by environmental groups about the impact of the project on wetlands, forests and rivers is "damaging the image of Northvolt and the credibility of our municipalities," Dulac and Lessard wrote.

"It is regrettable to see that your lack of transparency and leadership in this matter may deter foreign investors from proposing large-scale projects in Quebec," they wrote in their letter to Charette.

In March, Charetteacknowledged the government changed its rules regarding BAPE reports before approving the building of Northvolt a move that experts say has hindered public trust.

Before the project was announced, the province increased the threshold of battery production needed to trigger a BAPE review, raising it to 60,000 tonnes a year from 50,000.

Charette has said a full BAPE review would have taken 18 months and led the Swedish company to look elsewhere.

But he insisted"it was never the goal to get around the rules and avoid the BAPE."

Translated by Sabrina Jonas, based on reporting by Radio-Canada's Thomas Gerbet