Montreal's water meter saga continues

Montreal's controversial water meter contract will cost much more than the projected $356 million, according to city opposition leader Benoit Labont, who raised the issue of hidden costs during an extraordinary council meeting Tuesday.
Montreal opposition leader Benot Labont says the water meter contract could end up costing $500 million. ((CBC))
Montreal's controversial water meter contract will cost much more than the projected $356 million, according to city opposition leader Benot Labont, who raised the issue of hidden costs during an extraordinary council meeting Tuesday.

If incidental costs and inflation are factored in, Montreal taxpayers will be left with a $500-million bill over the next decade to install commercial water meters, Labont told city council.

Mayor Grald Tremblay called the extraordinary council meeting to review the water meter contract which is currently suspended until Montreals auditor general finishes analyzing how the tender process was handled.

The water meter contract was awarded two years ago to a Montreal-based consortium of companies GNiau which includes Simard-Beaudry Construction, a business under federal investigation for alleged tax fraud.

The construction companys owner, Tony Accurso, has been linked to former city executive president Frank Zampino. The pair spenttwo holidays together on Accurso'syacht while the contract tender bid process was open.

Zampino, who has since left municipal politics, denies showing the consortium any preference over other bidders.

He resigned from his new position as vice-president of Montreal engineering firm Dessauearlier this monthbecause of the water meter controversy. Dessau is also part of the GNiau consortium.

On Tuesday, municipal bureaucrats explained what the water meter contract entails, including installing commercial meters to regulate water use. They compared the costs to similar contracts in Ottawa and Toronto.

Tremblay urged the council to not draw any conclusions about the water meter contract until the citys auditor general finishes evaluating its contents.

Montreals impressive water leaks

Tremblay said Montreal is in dire need of commercial water meters, because the city wastes the equivalent of Paris daily drinking water supply every day.

About 40 per cent of Montreals water supply is wasted annually because of leaks and main breaks.

According to an engineering firm that helped Montreal formulate the water meter contract, Montreal is wasting a "fantastic" amount of water every year.

"The damage is very important," said Pierre Lavalle, president of BPR.

"The damages are very important from an ecological point of view, its surely not a good idea, and from an economic standpoint, the losses are fantastic."