20 metres down, 50 more to go: Crews make way for douard-Montpetit REM station - Action News
Home WebMail Saturday, November 30, 2024, 03:43 AM | Calgary | -15.5°C | Regions Advertise Login | Our platform is in maintenance mode. Some URLs may not be available. |
Montreal

20 metres down, 50 more to go: Crews make way for douard-Montpetit REM station

The Rseau express mtropolitain (REM) station will connect to the Mount Royal tunnel, about 50 metres deeper than the citys Metro line.

Station will be about 21 storeys below Montreal for the incoming light-rail network

The future douard-Montpetit station will be 70 metres below the surface. Blasting since October, crews have reached the 20-metre mark. (Jean-Sbastien Cloutier/Radio-Canada)

Pedestrians will need to watch where theystep near Universit de Montral's Marie-Victorin pavilion, as there's now a six-storeydeep hole in the ground and it's getting deeper every day.

No, it's not a wayward pothole. It's the site of the new light-rail train station slated to open by 2022, some 70 metres below the surface as thedouard-Montpetit Metro station's downstairsneighbour.

The Rseau express mtropolitain (REM) station will connect to the Mount Royal tunnel, about 50 metres deeper than the city's Metro line.Blasting for the new station began in October after three months of preparation.

Take a look into the douard-Montpetit REM site

6 years ago
Duration 0:37
The Rseau express mtropolitain (REM) station will connect to the Mount Royal tunnel, about 50 metres deeper than the citys Metro line.

But to cut so deeply into the bedrock just below a bustling city, crews have had to work in sections, carrying out targeted blasting operations in an effort to limit vibrationdamage to surrounding infrastructure and buildings.

The consortium securesabout 2,300kilograms of rubber matsto the site of the blast to help muffle the noise of up to four detonations a day, but these efforts have not been enough for some residents and a nearby school. Complaints have been piling up.

cole Saint-Germain d'Outremont officials met with REM representatives at the end of February to discuss the situation and work was temporarily suspended until an agreement could be reached.

Teams work most of the day

With new mitigation measures in place, blasts have since resumed as crews work to remove 30,000 cubic metresof rock,using baskets attached to cranes to haul the rock, mostly limestone, out of the hole and load it all onto trucks to be transported away.

The douard-Montpetit REM station will run underneath the douard-Montpetit Metro station, making it the second deepest station in North America. (CDPQ Infra)

That limestone is an "extremely hard rock, which is very hard to break," saidThomasFortin, who is managing the project forNouvLR, the consortium behind the project.

Two teams of 30 workers keep the site operating from 6 a.m. to 11 p.m. every day. The aim is to have the excavation completed by the spring of 2020 so construction can begin.

"It will then be time to fill the well with a station, adding all the architectural finish work, escalators and other elements," said Fortin.

The REM network is supposed to open by 2022. (CDPQ Infra)

The station will be one of the deepest in North America, falling second to Portland, Oregon's Washington Park light-rail station which is 79 metres down.

The douard-Montpetit REM station will allow passengers to travel from the Universit de Montral to downtown in just three minutes. It will be accessible by high-speed elevators that will carry an estimated 5,000 users per hour.

"There are going to be big elevators that will be able to go down the equivalent of 20 floors in about 20 seconds," said Fortin.

"From there, when users exit the elevators, they will end up in a station that will look like an STM station."

Crews prepare dynamite for blasting away sections of rock, mostly limestone, in preparation for the new douard-Montpetit REM station. (Jean-Sbastien Cloutier/CBC)

Light-rail network will have 26 stations

The station will be one of 26 stations on thenew 67-kilometre network. Those stations will be in places like downtown, Brossard, the West Island, Laval and at Pierre ElliotTrudeau Airport.

The $6.3-billion network is funded largely by the provincial and federal governments and its construction is being managed by CDPQ Infra, a subsidiary of the Caisse de dpt et placement du Qubec.

The consortium building the project includes firms SNC-Lavalin, Pomerleau, Dragados Canada, Aecon and EBC, but the trains will be manufactured in India by the consortium of Alstom Transport Canada and SNC-Lavalin.

Based on a report by Radio-Canada's Jean-Sbastien Cloutier and Jrme Labb