Opening of Paul Reynolds centre delayed until spring - Action News
Home WebMail Friday, November 29, 2024, 10:09 PM | Calgary | -17.1°C | Regions Advertise Login | Our platform is in maintenance mode. Some URLs may not be available. |
NL

Opening of Paul Reynolds centre delayed until spring

The opening of the Paul Reynolds Community Centre in St. John's has been delayed until the spring.

Community centre will replace Wedgewood Park centre

Work is continuing at the new community centre in the east end of St. John's but the building will not be ready to open in January. (City of St. John's)

The opening of the Paul Reynolds Community Centre in the east end of St. John's has been delayed until spring.

The facility, which is replacing the aged Wedgewood Park community centre, was set to open in January butran into construction delays.

According toCoun. DannyBreen, the city set a construction timeline that "may have been a bit too aggressive."

He said there werealso delays in getting some importantequipment, like hand rails, into the building.

"That delayed our commissioning. And now we're going through that process, and we certainly don't want to speed that up," said Breen.

"We want to make sure that we do all our checks."

A roundabout was constructed this summer at the entrance for the new Paul Reynolds Community Centre on Carrick Drive in St. John's. (City of St. John's)

Construction at thecentre began in 2014.

Breen saidthe project is still close to its budget of $32 million, despite the construction delays.

"So cost overruns are not an issue at this point."

The city saidregistration and rental information will be announced online once an opening date is finalized.