Asbestos delays demolition of old Whitehorse high school - Action News
Home WebMail Saturday, November 23, 2024, 05:31 AM | Calgary | -11.9°C | Regions Advertise Login | Our platform is in maintenance mode. Some URLs may not be available. |
North

Asbestos delays demolition of old Whitehorse high school

The Yukon Government says demolition of the old F.H. Collins high school in Whitehorse is over budget and behind schedule because of hazardous building material including asbestos.

Over budget and behind schedule, F.H. Collins demolition to be complete by summer, says gov't

Demolition of the old F.H. Collins building was originally expected to be complete by October, 2016. (Wayne Vallevand/CBC)

Demolition of the old F.H. Collins High School in Whitehorse is behind schedule and over budget.

The demolition project was expected to be complete this past fall, but now it will be next summer before it's all done.

Crews had expected some asbestos, but were surprised at the amount they discovered.

"What we encountered as we started the demolition project was additional hazardous building material including asbestos, so that has delayed the project by a few months," said Scott Milton, an assistant deputy minister with Highways and Public Works.

Scott Milton is the assistant deputy minister in charge of property management for the Yukon Government's Department of Highways and Public Works. (Wayne Vallevand/CBC)
Milton says the unexpected work and delays haveincreased the budget by $1.5 million dollars, from $4.5 million to roughly $6 million.

"People should start seeing signs of the school actually being removed or coming down mid-February to end of March," he said.

He says the new completion goal is June, 2017.

The interior of the school has been gutted and much of the contents repurposed to keep them out of the landfill.

"Inside the school, people who are familiar with F.H. Collins wouldn't recognize it," said Milton.

He added thatthe technical wing of the old school will not be torn down. It is beingupgraded and work on that section is expected to be finished by the end of January.

The Yukon Government covered over the original anticipated competition date and now says the project will be finished by June of 2017. (Mardy Derby/CBC)

with files from Mardy Derby