Atlin, B.C., hydro project testing starts without notice - Action News
Home WebMail Sunday, November 24, 2024, 12:56 AM | Calgary | -12.4°C | Regions Advertise Login | Our platform is in maintenance mode. Some URLs may not be available. |
North

Atlin, B.C., hydro project testing starts without notice

The small community of Atlin, B.C., was startled by loud explosions last weekend. The blasting, part of seismic testing related to a new hydroelectric station, was much louder than expected, says Peter Kirby, CEO of Tlingit Homeland Energy Limited.

Residents surprised by loud blasting noise before public consultation or environmental review

The MV Tarahne is a well-known landmark in the small community of Atlin, B.C., which was rocked by explosions last weekend. (CBC)

The small community of Atlin, B.C., was startled by loud explosions last weekend.

The blasting, part of seismic testing related to a new hydroelectric station, was much louder than expected, says Peter Kirby, CEO ofTlingitHomeland Energy Limited.

Peter Kirby, CEO of Tlingit Homeland Energy Limited, says the company has suspended work and will hold consultations in November. (CBC)

"Our mistake and I am ultimately responsible for this is that we didn't communicate early or effectively enough with the Atlin residents," he says.

Kirby says the sound reverberated because workers did not bury the explosive charges, a precaution taken toprevent therisk ofrom flying debris.

"Initially, in talking to consulting engineers, we were told this would be about the sound of a shotgun blast or a little bit louder," Kirby says."What actually happened, it turns out, was considerably louder than that."

Plans for microgeneration

Kirby says the company is testing bedrock to see if a new powerhouse could be built near Pine Creek Beach in Atlin.The proposed project would seek to generate aboutfivemegawatts.

Itwould be run and owned by the Taku River Tlingit First Nation through Tlingit Heritage Energy Ltd.

Thiswould be the second hydroelectric project in Atlin. A smaller, two-megawatt turbine was built in 2009 and supplies nearly all of Atlin's electricity.

Some residents opposed

Big sign outside of a building
The proposed hydroelectric project would be run and owned by the Taku River Tlingit First Nation government through Tlingit Heritage Energy Ltd. (CBC)

A few Atlin residentsdon't like the idea of the new project. Aform letter is being circulated among community membersurging them toask B.C.'s Ministry of Forests, Lands and Natural Resources to intervene.

The letter cites concerns over wildlife impacts the project could have on birds, fish and freshwater snails a "huge food source" for local trout.

"The area of Pine Creek Beach is a sensitive wetland and delta. It is host to many species that would be threatened by the destruction and erosion from a diverted creek," reads the letter.

"The current hydro plant produces sufficient power for the community. Excess power production is planned to be sold to the Yukon."

The letter also says the construction of power lines between Atlin and the Yukon would cause environmental damage.

Company promises consultation

Kirby says Tlingit Heritage Energy Ltd hoped to have information about bedrock stability and possible locations before launching consultations, but ithas now suspended work. He says the company will hold publicconsultations on the hydro generation projectin November.

Kirby says the project would go to environmental reviewafter a site is chosen.