Giant Mine remediation team discharging water into Baker Creek without licence - Action News
Home WebMail Tuesday, November 26, 2024, 07:56 AM | Calgary | -17.5°C | Regions Advertise Login | Our platform is in maintenance mode. Some URLs may not be available. |
North

Giant Mine remediation team discharging water into Baker Creek without licence

The Giant Mine Oversight Board is asking why the project team remediating Giant Mine is allowed to discharge treated water from the mine into Baker Creek without a licence.

'Anyone else would need a water licence,' says chair of board overseeing project

The Ingraham Trail outside of Yellowknife where it crosses over Baker Creek. The stream runs through the Giant Mine property and empties into Great Slave Lake. (Randall McKenzie/CBC)

The Giant Mine Oversight Board is asking why the project teamremediating Giant Mine is allowed to discharge treated waterfrom the mine into Baker Creek without a licence.

The water is pumped up from underground chambers, of which somehold tonnes of the arsenic trioxide dust.

The creek runs through the property and empties into Great Slave Lake.

The independent board posed the question in an annual report on the remediation effort at Giant Mine.

"At this stage we are a little unclear why it is okay for the project team to continue to discharge treated effluent without a water licence," said Kathy Racher, chair of the Giant Mine Oversight Board.

'Anyone else would need a water license,' says Kathy Racher, chair of the Giant Mine Oversight Board. (CBC)

"There may be good reasons for that, but we just don't know what they are... Anyone else would need a water licence."

The project team consists of officials with the federal and territorial governments.

An interview with the project team was not granted.

Instead, a spokesperson for Indigenous and Northern Affairs Canada (INAC) responded by email and said, "The Giant Mine Remediation Project team and the Minister of Indigenous and Northern Affairs have received the Establishment Report issued by the Giant Mine Oversight Board.

"Next steps will be determined once the Minister and the Project team have had time to review the Report and recommendations and give them the consideration they are due."

The frozen stream of Baker Creek. (Randall McKenzie/CBC)

The spokesperson pointed to INAC's website for more information.

According to the website, wastewater at Giant Mine is treated on site to meet or exceed the "the regulatory requirements set out in the mine's former water licence."

However, it doesn't spell out what those requirements are. Instead, it adds that the project team is proposing to bring water from the mineto drinking water standards of 0.01 mg of arsenic per litre.

It's unclear if that is currently happening.

According to a 2005 report titled Water Treatment Update Giant Mine Remediation Plan, the discharge standard under the former licence allows forarsenic concentrations of up to 0.5 mg/L or 50 times more than allowed for drinking water.

No one from the Mackenzie Land and Water Board, whichissues water licences, was immediately available for comment.

CBC News is awaiting further clarity from INACon what standards the project team is meeting with water treated at Giant Mine.

A road block entering Giant Mine. (Randall McKenzie/CBC)