UARB rules in favour of Hatchet Lake commercial development

The Nova Scotia Utility and Review Board has ruled that proposal by a developer to construct a fast food outlet and a gas bar in Hatchet Lake, N.S., does reasonably comply with the planning bylaws for the area.

Halifax and West Community Council had rejected project in September

Nova Scotia's Utility and Review Board has ruled in favour of a proposed commercial development in Hatchet Lake, N.S. (Hatchet Lake Plaza)

A commercial development will go ahead in Hatchet Lake, N.S., after a decision by the Nova Scotia Utility and Review Board.

The UARB ruled on Friday the proposal by Hatchet Lake Plaza Limited to construct a fast food outlet and a gas bar at 1656 Prospect Rd. does reasonably comply with the planning bylaws for the area.

The Halifax and West Community Council rejected the proposal at a public hearing last September. A petition with 578 signatures opposing the project was presented at the meeting. Local residents raised concerns about groundwater contamination, noise and increased traffic.

The developer appealed the community council's decision to the UARB and a hearing was held in early December. Peter Rogers, the lawyer for the developer, said at the time thatthe community council should not make decisions "based on petitions or popularity"but on whether or not the project is consistent with the planning rules.

The UARB agreed with the developer's arguments and has ordered council to approve a development agreement with Hatchet Lake Plaza Limited.