Ottawa buys light rail trains with no proven track record - Action News
Home WebMail Tuesday, November 26, 2024, 09:53 AM | Calgary | -16.6°C | Regions Advertise Login | Our platform is in maintenance mode. Some URLs may not be available. |
Ottawa

Ottawa buys light rail trains with no proven track record

The light rail vehicles that are one of the significant reasons for delays to Ottawa's $2-billion LRT project don't have a proven track record and are expected to make their North American debut in Ottawa.

The Alstom Citadis Spirit is specifically designed for North America but we'll be the 1st ones to use it

The Alstom Citadis Spirit light rail train was designed specifically for North America, but Ottawa will be the first to use it. (CBC)

The light rail vehicles that are one of thesignificant reasons for delays to Ottawa's$2-billion LRT projecthave noproven track recordandare expected to make their North American debut in Ottawa.

France-based companyAlstom,a member ofRideauTransitGroup theSNCLavalin-ledconsortiumbuilding the 13-stationConfederation Lineis supplying the trains for the project.

Alstom'sCitadisline of trainsis used in more than 50 cities in 20 countries, largely in Europe.

The company designed a new version of the light rail car, called theCitadisSpirit, specifically for the North American market that would be able to handle colder weather and winter conditions.

But although the provincial agencyMetrolinxhas purchased these same vehicles for two Toronto-area projects, "Ottawa will be the first North American city in which theCitadisSpirit will operate," according to anemailedstatement from Alstom.

'Fleet availability' issues

City officials said earlier this week they believe theLRT-completiondeadline will be missed a third time, even thoughRTGsaid it "anticipates" meeting the March 31 hand-over date.

One of the significant hold-ups is what OCTranspoboss JohnManconireferred to as a "fleet availability" issue.

In other words, not enough trains are ready.

Of the city's 34 vehicles, only 14 are completed enough or in good-enough working order to be tested along the entire 12.5-kilometre track.

Even then, only four to six vehiclesare being tested at a time, and it's not clear how many minutesthey are able to run in one shot.

The testing of the vehicles started in 2016.

10 vehicles don't have control system yet

The vehicleshave been assembled at OC Transpo's Belfast Yard facility where, among other things, they are retrofitted with the Thales control system.

Thales is the brain of Ottawa's automated light rail system, telling trains,for example, where exactly to stop on a station platform. (Although the trains are automated, a live, trained operator will be on board.)

Twenty-four of the light rail vehicles have been given safety certificates fromThales, according toMichael Morgan, the director of the city's rail construction program.

That doesn't mean they're ready for passenger service, but the certification isa milestone in the commissioning of the trains.

So 14 of these vehiclesare actually ready for full testing.

Ottawa Mayor Jim Watson said this week he does not believe that RTG will meet its March 31 deadline. (Alistair Steele/CBC)

But another 10, despite having their control systems green-lighted, are not able to be tested. They need "modifications," said Morgan.

Perhaps an error code that mistakenly comes up in the operator's car, or maybe a problem related to the doors, Morgan said by way of example.

He adds some issues are more complex, where workers have to get underneath the vehicle.

The final 10 cars? They don't have the Thales control system completed, even though the deadline for the entire Confederation Lineis less than seven weeks away.

Two vehicles are so unusable or at least not usable without a major amount of retrofittingthat RTG is going to swap them out for two vehicles that the city bought for the next phase of the LRT.

Panels have come loose at least twice

Last week, a panel came off one of the trains and caused some damage to the Bayview Station platform.

"We're still looking at the root cause of that, for why that may have happened," said Morgan, but added that it is not "raising any red flags" that it is a systemic issue.

Another panel was torn off a parked train during last September's tornado.

A replica of the Alstom Citadis Spirit was on display at Lansdowne in 2015. (CBC)

Even though they were unproven, the city agreed in 2017 to spend about $300 million on an additional 38 CitadisSpirit vehicles for Phase 2 of the LRT, the contract for which is supposed to be approved by council late this month.

"Would it have been nice to have a year of experience with the vehicles in service before, to take all those lessons and apply it to the later vehicles?" said Morgan.

"Yes, it would have been nice to have had that experience."

But he said now that the city has made its technological choice with the trains, it needs to stick with that decision, he said.

"We selected a vehicle, we selected a train control supplier," said Morgan.

"We need to carry those decisions through the stage two. We can't change midway through that process."