LRT handover pushed back, city says - Action News
Home WebMail Saturday, November 23, 2024, 04:05 AM | Calgary | -12.0°C | Regions Advertise Login | Our platform is in maintenance mode. Some URLs may not be available. |
Ottawa

LRT handover pushed back, city says

The City of Ottawa will need to wait a while longer before it gets the keys to its new light rail transit system from the consortium of companies building the project.

Rideau Transit Group has said meeting May 24 deadline could be 'risky'

A sign
The city has said its new LRT system will be up and running by 2018, but has not provided a specific date. (Trevor Pritchard/CBC)

The City of Ottawa will need to wait a while longer before it getsthe keys to its new light rail transit system from the consortium of companies building the project.

Rideau Transit Group (RTG)is getting extra time to deliver after telling the city that meeting the May 24, 2018, deadline would be risky.

In late November, RTGsaid the originaldeadline couldbe met, but that "delay events" catastrophic sinkholes, for example and contract changes might get in the way.

There's no incentive forRTGto drag this out. It's the opposite.- John Manconi, GM of transportation

So instead ofpushing it, the city is extending thehandover date, said transportation staff duringan LRTupdate at City Hall Friday.The new target date has not been announced.

While a handful of city officials, including Mayor Jim Watson, haveknown about the extension since November, the rest of council were only notified today, at the same time as the public.

"We're working with [RTG]to finalize the schedule so we can have that firmdate," saidJohn Manconi, general manager of transportation for the city.

Manconireassured residents the trains will start running sometime in 2018.

City could withhold funding

As part of its initial agreement with RTG, the city has the right to withhold monthly payments if the contractor does not meet agreed-to deadlines. The city can also impose a $1-million fine.

"The taxpayers will be protected," saidManconi. "There's no incentive for RTG to drag this out. It's the opposite."

But Manconiwould not say whether the city will actually impose those penalties.

The city will ask RTG to prepare a plan tominimize the delay.

Mandatory safety audit

Before RTG can hand over the system itwill have to finish construction on the new LRTstations, finish building all the trainsand test the overall system.

The sinkhole last spring made it difficult for the contractors to test the entire line. Instead they've created a "mini-system" that allows trains to run between the University of Ottawaand Blair stations for testing.

Theline will need to pass an independent safety audit before the city takes it over.

Manconi said Friday there's no date set for when the trains will finally start running, but pledged to provide councillorswith another update by March.