Trillium Line expansion 4 months behind, SNC-Lavalin told city in January - Action News
Home WebMail Friday, November 22, 2024, 12:49 PM | Calgary | -10.5°C | Regions Advertise Login | Our platform is in maintenance mode. Some URLs may not be available. |
Ottawa

Trillium Line expansion 4 months behind, SNC-Lavalin told city in January

SNC-Lavalin told the city in January that its work on extending the Trillium Line was almost four months behind schedule, which if not rectified means the rail expansion likely wouldn't be complete until early 2023, CBC News has learned.

City's rail managers told councillors Tuesday night about schedule 'challenges'

The Trillium Line was scheduled to be shut down for 28 months, and is scheduled to be substantially completed by August 2022. A recent update from the contract casts some doubt on that timeline. (Francis Ferland/CBC News)

SNC-Lavalin told the city in January that its work on extending the Trillium Line was almost four months behind schedule, which if not rectified means the rail expansion likely wouldn't be complete until early 2023, CBCNews has learned.

This week, senior managers with the city's rail office have indicated that the contractor on the $1.6-billion Trillium Line project has been experiencing schedule "challenges" and "pressures," adding that the city is working with the company to try to fix the issues.

But neither Michael Morgan, the city's rail director, nor John Manconi, the city's general manager of transportation, have publicly described the scope of SNC-Lavalin's reported delays, despite knowing about them since January.

In a 500-plus page schedule update report to the citydated Jan. 15, 2021, SNC-Lavalinstated that "the analysis indicates 116 days of delay" to the scheduled substantial completion date.

Construction is ongoing at the Carleton University Trillium Line station. The contractor told the city in January that it was 116 days behind schedule, which could push the rail system reopening into 2023. (City of Ottawa)

According to the city's contract with TransitNEXT, a subsidiary of SNC-Lavalin, the Trillium Line is supposed to reach substantial completion on Aug. 10, 2022. The city would still require more time before opening the system to the public, but it was always expected that the the Trillium Line, which serves Carleton University,would be operating in time for the start of the school year.

Based solely on the contractor's current predictions, the rail line wouldn't be open until the start of 2023.

The Trillium Line project is not officially delayed at this point.

No LRT2 update for months

Until this week, there has not been an official update on the O-Train extension program in almost four months. The last report was the third-quarter update that was released electronically in November 2020.

An update to the December meeting of council's finance and economic development committee was withdrawn. Nor was there any update to the committee at its next meeting in February, although the city's rail office would have been in receiptofSNC-Lavalin'supdated schedule.

The first update of the LRT situation was Monday of this week. In a memo to councillors,Morgan wrote:"The Trillium Line team has indicated schedule impacts which are now under review. The City is working with TransitNEXT to confirm whether the delays will be fully realized and to confirm if the delays can be reasonably mitigated. The handover of the system is still scheduled for 2022."

Ottawa rail construction director Michael Morgan, shown here in a 2019 photo, told councillors late Tuesday that the city is doing its own analysis of the Trillium Line schedule. (CBC)

In the same memo, Morgan indicated that the East-West Connectors the consortium building extending the Confederation Line has had "schedule pressures," but that they have been "resolved."

According to the contract, the scheduled substantial completion date for the eastern extension of the Confederation Line is Nov. 26, 2024 and for the western extension, May 25, 2025.

Late-night FEDco report

It wasn't until Tuesday at almost 10 p.m. that Morgan gave councillors an in-person update on the LRT Phase 2 progress. It followed an 11-hour joint-meetingof the finance and community and protective services committees.

The first item at the FEDco meeting chaired by Mayor Jim Watsonwas an in-camera session to hear an update on the city's ongoing legal dispute with the contractor of the first phase of the Confederation Line.

WATCH | Rail director says SNC-Lavalin previously disclosed delays:

How far behind is work on the Trillium Line? The city is looking into it

4 years ago
Duration 0:46
Michael Morgan, rail director with the City of Ottawa, says SNC-Lavalin previously disclosed delays to the Trillium Line extension, though city officials are conducting an independent review of how long the delays might be.

Morgan told councillors that the city doesn't just accept SNC-Lavalin'stimeline, and has its own scheduling experts studying the projections.

The city's believes the project could be behind as little as 40 days but, said Morgan, that analysis has "many qualifications and assumptions." He said he'd provide an update to the construction schedule in a month or two.

Watson asked whether the section betweenBayview to South Keys stations could operate before the entire line was open if the Trillium Line was delayed for "legitimate reasons."

"We haven't contemplated it at this point," said Morgan, adding his team would look into the possibility.

In a statement emailed to CBC, a spokesperson for SNC-Lavalinsaid the Trillium Line expansion project was deemed an essential service during the pandemic.

"The impacts related to manufacturing and the supply chain have been significant for our project as well as construction projects across the province," they said.

The company will try to mitigate schedule delays whereverit can, according to the email.

Add some good to your morning and evening.

More than the headlines. Subscribe to You Otta Know, the CBC Ottawa weekly newsletter.

...

The next issue of You Otta Know will soon be in your inbox.

Discover all CBC newsletters in theSubscription Centre.opens new window

This site is protected by reCAPTCHA and the Google Privacy Policy and Google Terms of Service apply.