First Nation calls on auditor general to investigate Ontario's spending on Ring of Fire mineral development - Action News
Home WebMail Friday, November 22, 2024, 01:45 PM | Calgary | -10.4°C | Regions Advertise Login | Our platform is in maintenance mode. Some URLs may not be available. |
Thunder BayCBC Investigates

First Nation calls on auditor general to investigate Ontario's spending on Ring of Fire mineral development

A Treaty 9 First Nation calls on Ontario's auditor general to investigate provincial spending on roads and development projects in the Ring of Fire area northeast of Thunder Bay to disclose who's paying and how much for the roads that must be built through several remote, fly-in First Nations.

14 years after Ring of Fire was discovered, key questions unanswered on proposed access roads

Ontario Auditor General Bonnie Lysyk gives a press conference.
A spokesperson for Ontario Auditor General Bonnie Lysyk, shown in a file photo, confirmed the office has received a request to investigate public spending on Ring of Fire development and road construction. (Aaron Vincent Elkaim/The Canadian Press)

A Treaty 9 First Nation is calling on the province's auditor general to investigate government spending on the development of a large mineral deposit in northern Ontario.

Neskantaga and a legal clinic with York University's Osgoode Hall have requested a "value-for-money audit" into government spending on roads and development projects in the Ring of Fire area, located about 540 kilometres northeast of Thunder Bay.

The public should be made aware if their government is spending public money on precarious mining investments with dubious returns while other sectors, namely health and long-term care, remain chronically underfunded.- Dayna Scott, Osgoode Law School, author of auditor general request

The province considers the area"one of the most promising mineral development opportunities in Ontario in over a century,"yet key questions remain about the roads that must be built through the lands and water systems of several remote, fly-in First Nations.

The Ring of Fire area is roughly 100 kilometres in diameter, and85 per centof the mineral claims staked on the Crown land are held by Noront Resources, according to a brief on their website.

The chromite-rich area known as the Ring of Fire is in the heart of Treaty 9, about 540 kilometres northeast of Thunder Bay. There is currently no road access to the region. (CBC)

Yetquestions remain about how much the roads will cost, who is going to pay for them, and who will own them and control access, said Dayna Scott, who wrote the request for the auditor general investigation.

"The public should be made aware if their government is spending public money on precarious mining investments with dubious returns while other sectors, namely health and long-term care, remain chronically underfunded," wrote Scott, an associate professor and research chair in environmental law and justice with York University.

A spokesperson for Ontario's auditor general confirmed to CBC News they have received and are assessing the request.

Road workmoves forward despite pandemic

The Ring of Fire mineral areais in the heart of Treaty 9 and made up of chromite, nickel and copper deposits. There is currently no road or rail access to the deposits, so it's been proposed thatthree all-season roads through the boreal forest and swampy peat lands of northern Ontario be built.

The 450 kilometres of new roads would connect several fly-in First Nationsas well as the mining depositsto the provincial highway network.

The map, provided by the Northern Road Link project team, shows the three proposed all-weather roads connecting remote First Nations to the provincial highway network. The Marten Falls Community Access Road is purple, the Northern Road Link is striped and the Webequie Supply Road is in red. (Supplied by Stephanie Ash)

Despite theglobal pandemic, several state of emergencies declared by First Nations in the area, and a moratorium declared earlier this year on all development in the Ring of Fire by three First Nations, the provincially mandated environmental assessments for each of the roads have moved forward in the last 18 months.

It's estimated the environmental assessments will be complete by the end of 2023, according to project guidelines from Noront Resources, which iscourting takeover offers by two Australian mining giants for the lion's share of mineral claims in the area.

No firmword on cost, ownership of roads

According to the letter written by Scott, thecost of the roads to the Ring of Fire is estimated at $1.6 billion, yet there is "no firm public commitments to Ring of Fire infrastructure funding."

Greg Rickford, provincial minister responsible for northern development, natural resources and forestryas well asIndigenous affairs, was unavailable for an interview, according to his press secretary.

CBC News asked the provinceto confirm the estimated $1.6-billion cost, as well as how it plansto pay for the construction of the roadsand who will own them.

A statement from the province said the proposed road infrastructure "would be available for both public and private use," but it did not answerquestions about cost or ownership of the roads. Instead, the statement saidtimelines and cost estimates will only become available after their environmental assessment.

However, documents obtained by CBC News showthe province has a cost estimate it's working with, and it has already asked the federal government for financial support of between $557 million and $779 million.

Rickford sent a letter and business case for Ring of Fire development to Infrastructure Canada on July 18, 2019, according to an access to information request released in August. It was estimated the overall cost would range from $1.1 billion to $1.6 billion, including funding for road planning and construction costs, environmental assessments, support for participants, and funding for well-being initiatives in nearby First Nations.

The business case includes a preliminary estimate for road planning and construction costs coming in at an average of $2.69 million per kilometre, based on technical studies completed by Hatch and Morrison Hershfield.

First Nationwants 'clarity'

Shortly after the Ring of Fire mineral deposits werediscovered in the late 2000s, Scott said,the mining companies involved in the early rush had proposed to take responsibility for developing the transportation corridor to get to the deposits, development of the mineand completing required environmental assessments.

But in recent years, the burden of paying for construction of the roads and the environmental assessments seems to have shifted to government and taxpayers, shesaid.

Dayna Scott, an associate professor and research chair in environmental law and justice with York University in Toronto, wrote the request for Ontario's auditor general to investigate the province's spending. 'The public should be made aware if their government is spending public money on precarious mining investments with dubious returns.' (osgoode.yorku.ca)

"That's the kind of issue we want to have clarity on.

"At what point did it become accepted that instead of the mining companies that want to profit from the extraction of these minerals paying for the road to access them that Ontarians would be paying for these roads?"

Scott said she hopes the auditor general, who reports to the OntarioLegislature, will allow for greater accountability and transparency on government spending.

"First Nations communities in Ontario's Far North who have been disproportionately burdened by the pandemic and are bearing the heaviest climate change burdens deserve answers as to how and why Ontario is supporting contested mining developments in their homelands," concluded Scott in her letter to the provincial auditor general.

Securities commission complaint filed

This is just the latest effort byOsgoode Hall Law School's Environmental Justice and Sustainability Clinic to get more information on activities in the Ring of Fire.

A group of organizations including the legal clinic, Greenpeace Canada, the Council of Canadians and MiningWatch Canada asked the Ontario Securities Commission in August 2021 to investigate whether the extent of Indigenous opposition to Ring of Fire development has been reported by Noront Resources.

The company has "ownership or a controlling interest of all the major discoveries in the Ring of Fire to date," according to itswebsite.

The coalition of organizations reviewed Noront's disclosures from 2015 and onwards.

In their letter to the securities commission, they said"it appears that Noront has failed to provide a fulsome account of the vocal dissent voiced by various First Nations in the region in relation to its assets and projects with the potential for misleading investors."

The letter added it hopes an investigation will lead to more accurate reporting by Noront and other companies regarding their relationships with Indigenous communities affected by their business activities.

Noront's chief executive officer, Alan Coutts, was not available for an interview.

A spokesperson for the Ontario Securities Commission said it could not confirm or comment on the existence, status or nature of any complaint, review or investigation, as a matter of policy.