B.C. First Nation says feds may have approved Kinder Morgan pipeline expansion before finishing consultations - Action News
Home WebMail Saturday, November 23, 2024, 12:05 AM | Calgary | -11.5°C | Regions Advertise Login | Our platform is in maintenance mode. Some URLs may not be available. |
Politics

B.C. First Nation says feds may have approved Kinder Morgan pipeline expansion before finishing consultations

A British Columbia First Nation is questioning the greenlighting of the Kinder Morgan Trans Mountain pipeline, arguing there may be new evidence the federal government failed to complete consultations with First Nations prior to approving the expansion.

The Tsleil-Waututh Nation is preparing to ask court for release of federal Trans Mountain pipeline documents

The Tsleil-Waututh Nation has filed a letter with the Federal Court of Appeal questioning whether the federal government failed to complete First Nations consultations with First Nations before approving the Kinder Morgan Trans Mountain pipeline's expansion.

A British Columbia First Nation is questioning the greenlighting of the Kinder Morgan Trans Mountain pipeline,arguing there may be new evidencethe federal government failed to completeconsultations withFirst Nations prior to approving the expansion.

In a letter filed to the Federal Court of Appeal on Thursday, the group's lawyer, Scott Smith, says two stories published in April by the National Observer, a national news website,confirmed theTsleil-WaututhNation's fears that the government had acted improperly.

Citing documents laid out in the two media reports, Smith's letter saysthat government employees were instructed to give cabinet a legally sound basis to approve the pipeline at the sametime the government was still supposedly consulting with First Nations and had not reached a decision yet.

The Tsleil-WaututhNation intends to bring forward an urgent motion requesting that the federal government be ordered to produce thedocumentsand if necessary, will bringanother motion to allownewevidence to be heard in court in order to ascertain whetherthe government breached its duty to consult with the Tsleil-Waututh Nation.

"Canada represented to the parties and the Court that it had appropriately and meaningfully consulted with TWNwhen it now appears Canada had already pre-determined that it would approve the Project," the letter says.

Bill Morneau on saving Kinder Morgans Trans Mountain Pipeline

6 years ago
Duration 6:33
Finance Minister Bill Morneau is tasked with saving the Trans Mountain pipeline. He speaks with CBCs Wendy Mesley about the ongoing battle to get the pipeline expansion built, and how the outcome will affect the Liberals come election time.

This new potential evidence of "bad faith" and "dishonourable conduct" could have bearing on the court's decision as to whetherthe government discharged its duty to consult, Smith's letter states.

The first motion is expected to be filed next week,a source with knowledge of the court proceedings told CBCNews.

Should that motion be approved, it would likely add more than a month to the timeline for the case.

Last fall, seven First Nations, the cities ofBurnabyand Vancouver, and two environmental groups asked the court to overturn the federal government's decision to approve the expansion of the $7.4-billion pipeline from Edmonton toBurnaby.

This new letteris unusual, since the casewhich includedthe Tsleil-WaututhNation was heard in the fall. However, Smith says in the letter there is legal precedent for the court to reopen the matter.

Pushback from government, pipeline company

In a written response from the federal governmentobtained by CBC News, it outlines ithasno position on whether the First Nation should be "permitted to bring this motion at this late date, over six months after the hearing of these proceedings has concluded."

That letter also explains the government does not see the motion as "urgent," but asks the court that if the motion is allowed to proceed that the timeline be brief 10 days for a government response after the motion, and four days for theTsleil-WaututhNation to reply.

In a statement provided to CBCNews, Kinder Morgan said this motion would cause unnecessary delay to the case, as a decision was expected this spring.

The company argues reopening the case now would cause "significant prejudice" against Trans Mountain. In their own letter to the court, they ask for the proposal fromtheTsleil-WaututhNation to be rejected.

While 43 First Nations havefinancial benefit agreements with Kinder Morgan in support of the new pipeline, the Tsleil-Waututh and severalother nations along its path oppose it.

The Trudeau government approved the project in November 2016 after the NEB recommended it get the green light, subject to 157 conditions.

So far, the NEB has approved 66 per cent of the project's proposed detailed route and hearings are scheduled to continue on the project into the fall, according to the regulatory body.

Kinder Morgan has engaged with 133 Indigenous communities and groups in Alberta and B.C. over the last six years on the project.